PSE&G Seeks Deferral Order to Recover Capital Costs Before 2027 Rate Filing
Sun, November 15, 2026Public Service Enterprise Group’s New Jersey utility, PSE&G, has asked the New Jersey Board of Public Utilities for a deferral accounting order aimed at addressing regulatory lag on capital investments made since its last distribution rate case.
The proposal, disclosed in a November 6 regulatory filing and discussed in PSEG’s November investor update, would allow the utility to defer certain costs beginning in January 2027 until new rates take effect. PSE&G said the framework would preserve a June 2027 date for its next electric and gas distribution base-rate filing while keeping base distribution rates stable during the deferral period.
Regulatory timing is central to PSEG’s investment plan
For PSEG, the request is significant because the company is pursuing a regulated capital investment program of approximately $22.5 billion to $25.5 billion from 2026 through 2030. The company expects that spending to support regulated rate-base growth of roughly 6% to 7.5% over the period, with projects focused on grid modernization, reliability, gas infrastructure replacement and clean-energy programs.
Deferral accounting could help reduce the earnings lag between when infrastructure is placed in service and when customer rates begin reflecting the associated investment. The arrangement would still require review by the BPU, including a determination of whether the underlying expenditures were prudent and eligible for recovery.
PSEG’s investor materials also said the proposal is intended to align with New Jersey’s energy-policy goals while maintaining customer affordability. PSE&G reported that residential gas heating bills were reduced by 5% effective October 2026 and that the utility continues to maintain among the lowest gas bills in New Jersey and the Mid-Atlantic region.
Additional transmission benefit expected in 2027
The company is also preparing to benefit from a separate transmission cost-allocation development at PJM. PSEG said a PSE&G-led effort at the Federal Energy Regulatory Commission resulted in a prospective reduction in costs for the utility’s wholesale transmission customers.
PSE&G expects to file in early 2027 to credit retail customers for the reduction. PSEG estimates the related regulatory-asset benefit at approximately $65 million annually beginning in 2027, according to its investor update.
Separately, PSE&G filed an annual transmission formula-rate update with FERC in October. The filing is expected to produce approximately $60 million in higher annual transmission revenue effective January 1, 2027, subject to a later true-up.
PEG shares finish the week higher
NYSE-listed PEG closed at $75.88 on November 13, 2026, up 0.77%. The share-price move is reported separately from PSEG’s regulatory disclosures because the available company materials do not establish that the deferral request or transmission developments directly caused the day’s performance.
The regulatory filing nevertheless gives investors a clearer view of how PSEG is attempting to manage the timing of cost recovery as its investment program expands. The next major milestone is the BPU’s consideration of the deferral proposal, followed by PSE&G’s planned June 2027 distribution base-rate filing.